thomas.vanparys
Hi,
I've been searching for an add-in to MSP2K (standalone) which would
extend the Resource Leveling capabilities to allow it to switch around
resources based on skills and availabilities.
Such a tool would require the ability to manage resource groups and
individual resource availabilities within the groups. It would extend
MSP to allow the assignment of a group to a task rather than an actual
resource. When levelling the project MSP would then work out the best
possible shedule based on resource availabilities within the pool.
Has anyone come accross such a tool?
Thx
Thomas V
I've been searching for an add-in to MSP2K (standalone) which would
extend the Resource Leveling capabilities to allow it to switch around
resources based on skills and availabilities.
Such a tool would require the ability to manage resource groups and
individual resource availabilities within the groups. It would extend
MSP to allow the assignment of a group to a task rather than an actual
resource. When levelling the project MSP would then work out the best
possible shedule based on resource availabilities within the pool.
Has anyone come accross such a tool?
Thx
Thomas V