Resource Leveling - Cash

T

Tyson

The resource leveling is a very useful tool I recently discovered in Project
2007. I would like to know if there is a way to apply this tool to cash as a
available resource. My team is allocated a fixed amount of money on a monthly
basis. The money is accured if it is not used. Is there a way to determine
when tasks can be completed based on available cash? If so, how can I do
this? If not, are there any Microsoft partners that have developed software
to do this effectively?
 
J

Jan De Messemaeker

Hi,

Unfortunately, as you have discovered, Material and Cost resoruces cannot
influence the plan: you cannot even define how much you have left :-(

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 