Resource information by individual project

S

Suzanne

I would like to view resource information for each resource by individual
project. I realise I can use filters to show Pxxx only, however the summary
line still reflects totals for all projects assigned to resource. I have
also tried exporting via Analyse Timescaled Data in Excel (filtered by Pxxx)
but again the result is totals for all projects assigned to resource. If I
open the Resource Profile it lists summary of projects assigned under each
resource but again to export this data I end up with summary of all projects.


I could get the result I'm after by copying and pasting data from project to
excel and then manuplating data there but is there an easier way to export (&
view) resource information for each resource by individual project.

Thanks
 
P

Paul Conroy

Have you tried loading Proj Pro without summary resources and then reporting
from reports\visual reports ?
 
S

Suzanne

How do I load without summary resources?

I know there is a check box in Options, View, "Show Project Summary Task",
is there another check box somewhere for summary resources?

Thanks!
 
M

Mike Mahoney

How do I load without summary resources?

I know there is a check box in Options, View, "Show Project Summary Task",
is there another check box somewhere for summary resources?

Thanks!






- Show quoted text -

Alternatively you can group on resource name in the resource usage
view and filter out external tasks

regards

Mike
 
Top