Resource Leveling and lag

T

Tom

I have a Task Dependency (FS) between two tasks (lag 0d).
How can I prevent that there will be a "lag" between the
two tasks when I use Resource Leveling?
SOme tasks in my project plan have to start immediately
when predessor finishes.

Thanks in advance,
Tom
 
D

Dale Howard

Tom --

It sounds like the tasks which should not be delayed are higher priority
tasks than some others which should be delayed. Double-click those higher
priority tasks, select the General tab, and set the Priority number to a
value higher than the lower priority tasks. The default Priority number for
every task is 500, so you should set the Priority greater than 500. Hope
this helps.
 
M

Mike Glen

.......or even set the priority to 1000 which means "do not level".

Next time, please post this on the project newsgroup, as this one is closing
down! Please see FAQ Item: 24. Project Newsgroups. FAQs, companion
products and other useful Project information can be seen at this web
address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 
Top