Resource Leveling Problem

A

Akram

Hi,
I am using leveling in microsoft project professional with no problem,
however when i use it when connect to the project server, i face the
following problem with leveling:

I have a resource assigned to 2 tasks at the same time and schedule, when i
do leveling it assigns the resource the first task accordingly, however it
assigns the second resource 2 weeks from its date, although the first task is
only 2 days. i tried seeing the availability and found it was not utilized
for a whole week. The leveling delay field shows 10 days leveling delay !!

i used the following settings with leveling:
1. ID Only
2. all values are unchecked
3. Manual
4. Hour by Hour

i tried using it with different settings but with no success, can someone
please help me out.
 
R

Reid McTaggart

Some possibilities leap to mind:
1) Is there another resource assigned to the second task?
2) Is there a task calendar on the second task?
3) Have you checked the resource's calendar?
 
A

Akram

The second task is assigned to the same resource, so it should level
accordingly, however it levels the second task after 2 weeks from the end of
the first task !!

There is a project calendar no task calendar in project server

The resource calendar is using the same as project calendar, note they are
both using an enterprise calendar.
 