I am having a problem leveling my resources. I have been
told the best way to do this is in the 'enterprise
resource sheet'. When I level the resources, nothing
happens to any of my project start dates. I have
prioritzed my proejcts, giving a priority of 1000 to those
that I don't want to be leveled. I have no constraint
dates. I am using "priority, standard" leveling, no other
boxes are checked. I am using a leveling range of "entire
project". I am using a leveling calculation of "manual,
day by day". Should I be doing this in the 'enterprise
resource sheet' or in the projects themselves? Any help
would be greatly appreciated. I am relatively new to this.
told the best way to do this is in the 'enterprise
resource sheet'. When I level the resources, nothing
happens to any of my project start dates. I have
prioritzed my proejcts, giving a priority of 1000 to those
that I don't want to be leveled. I have no constraint
dates. I am using "priority, standard" leveling, no other
boxes are checked. I am using a leveling range of "entire
project". I am using a leveling calculation of "manual,
day by day". Should I be doing this in the 'enterprise
resource sheet' or in the projects themselves? Any help
would be greatly appreciated. I am relatively new to this.