Kelly O
Scenario: Resource 1 is assigned 16 hours of effort to be completed between
9/21 and 9/22. During that period, Resource 1 completed 12 of the 16 hours.
On 9/27, the PM reviews the schedule and levels, but the remaining hours on
the task (and scheduled Finish date) do not move to a future time period.
Is there a setting for MSP to move the Remaining Work forward?
9/21 and 9/22. During that period, Resource 1 completed 12 of the 16 hours.
On 9/27, the PM reviews the schedule and levels, but the remaining hours on
the task (and scheduled Finish date) do not move to a future time period.
Is there a setting for MSP to move the Remaining Work forward?