Resource Levelling is set to "Automatic" by default

S

Sylvia de Hart

One of our customers claims that, after having freshly installed MS Project
2007 on a stand-alone workstation, the Resource Levelling is set to
'Automatic'.
They prefer this setting, after a fresh installation, to by default be
'Manually'.
What can I adivise them?
 
J

Jan De Messemaeker

Hi Sylvia,

I've never seen this.
You don't give me much hope - fresh install does not allow to enter this
kind of parameter
Are you very sure there wasn't an old global.mpt present in the standalone
machine?

Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620