Resource Levelling of resources across workplan

P

paulli

How do you manage over allocation of resources that are spread across
multiple workplans and releases?
 
R

Rod Gill

The first thing you have to do is get resource managers and project sponsors
to agree project priorities and to then allocate a certain number of hours
per week for each resource to each project. Now the PM levels to the hours
per week they have been given.

--

Rod Gill
Microsoft MVP for Project