Resource Levelling

D

David

Hi,
How to stop automatic resource levelling on the Project
Server while publishing project plans? This is causing
changes in Project Finish Date.

Regards,
David
 
D

Deepu Chacko

1. Open Project Professional.
2. Open your project.
3. Click on Tools -> Level Resources
4. Select the radio button "Manual" under Leveling Calculations section.

This should do the trick for u, let me know how it went ...
 
D

David

Deepu,
I would like to set this at the Project server level
so that when each PM publishes the plan, the levelling is
controlled. Any idea?
Regards,
David.
 
G

Gary Chefetz [MVP]

David:

The best you can do is to force project creation through templates, or write
a macro.

--
Gary Chefetz [MVP]
http://www.msprojectexperts.com

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 