C
CarliC
I am brand new to having to load a schedule with resources.
I work in construction and have built a very large schedule in projects, the
client has now asked that I "resource load" this.
I have over 100 tasks to complete and I need to find out how I can load each
task by quantity if possible.
I.e.: Task 10 - Topsoil Stripping... I will need 1 foreman, 10 operators
and 6 laboures working 3 days to complete this task plus all relevant
equipment.
Can anyone tell me the best way to enter this without having to enter
"operator" 10 times over for each task so that projects accounts for it?
Please help, stressed and under a tight deadline.
Thanks,
Carli
I work in construction and have built a very large schedule in projects, the
client has now asked that I "resource load" this.
I have over 100 tasks to complete and I need to find out how I can load each
task by quantity if possible.
I.e.: Task 10 - Topsoil Stripping... I will need 1 foreman, 10 operators
and 6 laboures working 3 days to complete this task plus all relevant
equipment.
Can anyone tell me the best way to enter this without having to enter
"operator" 10 times over for each task so that projects accounts for it?
Please help, stressed and under a tight deadline.
Thanks,
Carli