I
Ian Wolstenholme
Hello,
I have a particular scenario in which I need to report on the department for
each resource over time. But the resources change departments on a regualr
basis. What I need is someway of recording this ....
For example Bill is one of my resources. His movement are as follows :-
2nd January Homologation Department
12th January Regulatory Department
16th February Current Affairs
5th April Legal
14th June Homolgation Department
All other resources get assigned in a simialr way.
However I haven't found a way to record this anticipated or historic
movement of resources from department to department, which makes it very
difficult to predict resource workload over time for a given department.
Does anyone have any suggestions as to how this can be done ?
Thanks
Ian
I have a particular scenario in which I need to report on the department for
each resource over time. But the resources change departments on a regualr
basis. What I need is someway of recording this ....
For example Bill is one of my resources. His movement are as follows :-
2nd January Homologation Department
12th January Regulatory Department
16th February Current Affairs
5th April Legal
14th June Homolgation Department
All other resources get assigned in a simialr way.
However I haven't found a way to record this anticipated or historic
movement of resources from department to department, which makes it very
difficult to predict resource workload over time for a given department.
Does anyone have any suggestions as to how this can be done ?
Thanks
Ian