Resource Manager access to projects

J

June H.

. Reply (E-mail) Forward (E-mail)

Subject: EPM Web project access
From: "June Higgins" <[email protected]> Sent:
10/7/2003 2:01:47 PM




I developed a new category to be used by specific internal
managers to manage a specific pool of resources within the
enterprise resource pool. In the new category I want to
allow these internal managers to view only the projects
that their specific resources are assigned to.
I selected all four check-boxes under the project section
of the category, including the one that allows the user to
view all projects assigned to a resource they manage, but
it does not seem to allow the internal managers access to
the projects that their resources (specified pool)are
assigned to.

The question is: is there any way to indicate that a user
manages a resource other than publishing a project where
the resource is assigned?

Is there any other way I could restrict the projects that
these internal managers can view? (other than selecting
the specific projects)
 
K

Kevin Flanagan

The correct method is to use your RBS code (Enterprise
Resource Outline Code30)to show your org structure. Once
this is in place, your managers will only be able to see
those projects and resources that are in their RBS
structure.
 