I am getting a meassage in the resource sheet that sais "this resource should
be levered based on a Day to Day setting"- what does that mean and what
should i do?
 
G

Gérard Ducouret

Petra,

You probably assigned this resource on 2 tasks running in parallel. So you
have to level the workload of that resource:
Tools / Level resource...
Hope this helps,

Gérard Ducouret
 