Resource Overallocation

J

JoeP

In Project 2003 is there a view that will show me the tasks that are causing
a resource to be overallocated?
 
M

Mike Glen

Hi Joe,

Welcome to this Microsoft Project newsgroup :)

Try the Resource Allocation view and apply the filter for Overallocated
Resources.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
Top