Michael Brown
Running into some interesting issues using "Team" resources on a resource plan.
1) We seem to ONLY be able to enter Team Resources as FTEs. When using
"Hours" or "Days" we get an error message indicating the unit of measure is
invalid. FTEs, hours or days works just fine for non-team resources.
2) When we enter values for a Team Resource and publish the resource plan,
some of the columns of information seem to have 'random' numbers appearing.
For example, if I enter .5, .6, .7 for January, February and March of 2008,
when the publish is complete, we may get .5, .19, 0.
Anyone run into anything like this using Team Resources on a resource plan??
1) We seem to ONLY be able to enter Team Resources as FTEs. When using
"Hours" or "Days" we get an error message indicating the unit of measure is
invalid. FTEs, hours or days works just fine for non-team resources.
2) When we enter values for a Team Resource and publish the resource plan,
some of the columns of information seem to have 'random' numbers appearing.
For example, if I enter .5, .6, .7 for January, February and March of 2008,
when the publish is complete, we may get .5, .19, 0.
Anyone run into anything like this using Team Resources on a resource plan??