Resource Pool Location

M

MarkP

I have a macro that spins thru the Project Central List of projects (Inspired
by Rod Gill - Thanks) to performa a number of tasks.

What I want to do is be able to re-point the projects to a new resource pool
as part of repairing a corrupted pool.

My question is: where is the name of the resource pool stored within a
sharer project. And, can I change it using VBA?
 
M

Mike Glen

Hi Mark,

Try posting on the microsoft.public.project.server newsgroup (forum). Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP


I have a macro that spins thru the Project Central List of projects (Inspired
by Rod Gill - Thanks) to performa a number of tasks.

What I want to do is be able to re-point the projects to a new resource pool
as part of repairing a corrupted pool.

My question is: where is the name of the resource pool stored within a
sharer project. And, can I change it using VBA?
 