S
Steve Scott
I am working in a non-Project Server environment and have set up a Resource
Pool, a Master Plan and several individual project plans. I am also about to
implement a "working" plan and "published" plan versioning system that
requires Project Managers to maintain and work with their Working Versions
but only publish them (ie save or email to PMO) each week which will
overwrite the Master Plan sub-projects as the approved versions.
My concern is when they update and save changes to their working versions of
their plans, this will force an update of assignment infrmation to the
Resource Pool which is itself linked to the Master Plan which is linked to
the previous week's versions of the published plans - if that makes sense...?!
Is it the case that the previous week's published plans will then be updated
by changes coming from the updated Resource Pool or are these plans loaded
into the Master Project disconnected from updates in some way? Is there an
issue here or am I fretting unecessarily? If there is - what is the work
around as I do not want Project Managers working on the published plans
directly loaded into the Master Project but I do want their working copies to
be connected to the Resource Pool.
Pool, a Master Plan and several individual project plans. I am also about to
implement a "working" plan and "published" plan versioning system that
requires Project Managers to maintain and work with their Working Versions
but only publish them (ie save or email to PMO) each week which will
overwrite the Master Plan sub-projects as the approved versions.
My concern is when they update and save changes to their working versions of
their plans, this will force an update of assignment infrmation to the
Resource Pool which is itself linked to the Master Plan which is linked to
the previous week's versions of the published plans - if that makes sense...?!
Is it the case that the previous week's published plans will then be updated
by changes coming from the updated Resource Pool or are these plans loaded
into the Master Project disconnected from updates in some way? Is there an
issue here or am I fretting unecessarily? If there is - what is the work
around as I do not want Project Managers working on the published plans
directly loaded into the Master Project but I do want their working copies to
be connected to the Resource Pool.