Resource pools and resource leveling

W

Walid

Hello:

I know we can create resource pools within Project Pro 2007. Is there a way
to create resource pools within Project Server? Can resource pools be used
for resource leveling?

Thanks,

Walid
 
J

Jan De Messemaeker

Hi,

The enterprise resource pool IS a pool.
Leveling will act like with a resource pool: tasks from open projects can be
delayed, tasks in Proejcts that are not open are considered immovable.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620