R
Ritsaert
Hi,
I'm implementing MS EPM 2007 at a client at the moment. One of the main
goals of the client is to improve the process of resource utilization. I'm
having trouble to facilitate this with EPM.
What I would like to do is:
- with a new project let a project manager request a resource
- let the resourcemanager recieve this resource request
- give the resourcemanager the opportunity to approve/deny the resource
request
- let the projectmanager assign the resource in his project
Is there some functionality that I am overlooking?
Thanks in advance for helping me out!
Regard,
Ritsaert
I'm implementing MS EPM 2007 at a client at the moment. One of the main
goals of the client is to improve the process of resource utilization. I'm
having trouble to facilitate this with EPM.
What I would like to do is:
- with a new project let a project manager request a resource
- let the resourcemanager recieve this resource request
- give the resourcemanager the opportunity to approve/deny the resource
request
- let the projectmanager assign the resource in his project
Is there some functionality that I am overlooking?
Thanks in advance for helping me out!
Regard,
Ritsaert