B
Bob
I am new to MS Project and in particular the newer
versions. Does MS Project (what version) allow me to
have a shared pool of resources (say enterprise level)
that can be assigned to department projects on a non-
exclusive basis. For example, Bob may be assigned 50% to
Project A and 50% to Project B, both being run by two
different PM's. They each build their schedule in a
their own Project file. Do you have to merge those two
projects into a single project and run the resource
leveller? If one of them asked for Bob at 60% how does
it let you know about the overload.
Sorry for the detailed questions but I want to figure out
if this is a good tool for our needs
versions. Does MS Project (what version) allow me to
have a shared pool of resources (say enterprise level)
that can be assigned to department projects on a non-
exclusive basis. For example, Bob may be assigned 50% to
Project A and 50% to Project B, both being run by two
different PM's. They each build their schedule in a
their own Project file. Do you have to merge those two
projects into a single project and run the resource
leveller? If one of them asked for Bob at 60% how does
it let you know about the overload.
Sorry for the detailed questions but I want to figure out
if this is a good tool for our needs