Given some resources shared between ProjectA and ProjectB, can I make tasks
assigned in ProjectA (with higher priority) appear as non working days in
the resource calendar of Project2?
Regards
Mario
 
J

Jan De Messemaeker

..... at least if they are connected to a same resource pool or to Project
Server.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
Gérard Ducouret said:
Mario,

No, you cannot do that, but in a view such as Resource Usage, you are able
the look at the availability of any resource, taking in account all
his/her assignments in any project.
--
Gérard Ducouret

[Project MVP]
www.pragmasoft.fr
Un livre sur Project Server 2007 pour le Chef de projet:
http://www.lmet.fr/advsearch.cgi?_EXPRESSION=ducouret&_DISTANCE=10&_PAGE=1


Mario - Roma said:
Given some resources shared between ProjectA and ProjectB, can I make
tasks assigned in ProjectA (with higher priority) appear as non working
days in the resource calendar of Project2?
Regards
Mario
 