Resource Sheet Concatenation

S

Steve

If I have two projects up on the Project Server, call them Project A
and Project B, and I open them at the same time, MSP concatenates their
resource sheets - i.e. Project A has 5 resources and B has 10... when I
open them both, the resource sheets in both projects show 15 resources.
Is there any way to filter this out or to stop this behavior? I tried
the Project field, but all it shows is "Published".
 
S

Steve

Anybody have any ideas? I'm plain stumped, and I know it's probably an
option somewhere...
 
D

Dale Howard [MVP]

Steve --

There is no option anywhere to eliminate this behavior as it is the default
behavior of enterprise projects in Project Server. Sorry.
 