B
Barbara
Am I missing something obvious? I want to create a
resource table that shows Work for the particular project
I have open, however, the hours that display are for all
published projects. I've tried filtering by "Project Team
Members" but still see all published hours, not just work
for the particular project. Is there some sort of filter
I can set that I haven't found?
Also, is there a way to associate a custom resource field
with work per task? Would like to create a custom task
field that multiplies a custom resource cost field with
work but haven't had any luck.
Any advise much appreciated!!!
resource table that shows Work for the particular project
I have open, however, the hours that display are for all
published projects. I've tried filtering by "Project Team
Members" but still see all published hours, not just work
for the particular project. Is there some sort of filter
I can set that I haven't found?
Also, is there a way to associate a custom resource field
with work per task? Would like to create a custom task
field that multiplies a custom resource cost field with
work but haven't had any luck.
Any advise much appreciated!!!