Tim
I have a global resource who is new to my project, who is replacing a
resource that has left. The resource who left has actual hours recorded, and
naturally, I need to keep those actual hours associated with the proper
resource. Ideally, I would like to take the remaining work of the resource
who left and assign it to the new resource. Is there an easy way to do this?
A second related problem--As a work-around in case there isn't an easy way
for the new resource to assume the old resource's remaining work, I thought
the new resource could assign herself to an existing task in Project Web
Access. She couldn't because the "Project" box wasn't populated with
available projects (presumably because she is not assigned to any activities
in my project). Is there a way to assign her to tasks in my project (if she
cannot assume the remaining work of the resource who left)?
resource that has left. The resource who left has actual hours recorded, and
naturally, I need to keep those actual hours associated with the proper
resource. Ideally, I would like to take the remaining work of the resource
who left and assign it to the new resource. Is there an easy way to do this?
A second related problem--As a work-around in case there isn't an easy way
for the new resource to assume the old resource's remaining work, I thought
the new resource could assign herself to an existing task in Project Web
Access. She couldn't because the "Project" box wasn't populated with
available projects (presumably because she is not assigned to any activities
in my project). Is there a way to assign her to tasks in my project (if she
cannot assume the remaining work of the resource who left)?