Marc --
The RBS field is not a multi-value (MV) field, therefore, you must select a
single value for each resource in this field. The RBS field is used in the
Project Server security model to show "who reports to whom" and is used for
both project and resource security in Categories. If you are using Project
Server 2003, you could use enterprise resource outline code fields #20-29 as
they are all multi-value fields. Without seeing exactly what you are trying
to do with the RBS field, I'm not sure I can comment in anything more than
general terms. Hope this helps.
Marc Daoust said:
Hello,
Is it possible to assign a resource at multiple levels of an RBS? If yes,
how? If not, can you recommend any way to get arround this?