Regarding your question about fixed duration tasks being extended, that
has happened to me many times, and the reason is actually in the error
message!. A user enters more actual time than there was work remaining on the
task. The finish date is set, normally, to the last day of work, so if work
is logged later than the current finish date, finish date HAS to change.
Being a fixed duration task, that generates the message.
Regarding the original issue, are these "pantom" actuals in colored
font, or black font? If black, that represents time that THEORETICALLY was
passed from PWA to Professional, then saved/pblished from Professional.
Colored font indicates time enter by a user in PWA, and not yert updated.
The next time you see "phantom" actuals in on a task in some week, open
the project in Professional, and use "Task Usage" view to see if those
actuals are showing up in the same week. If so, I can, with 99.9% certainty,
say the PM overseeing that project adjusted actuals in some way, and
re-published assignments with an override of actuals. I can think of no other
way, short of direct SQL manipulation! :>)
Marc is correct that a detailed description of what you are doing and
seeing would help lots!
FWIW ...
JTC