Resource to work 2 days a week?

K

kellycell

Hello,

I have a resource in my project that can only work 2 days per week on
the tasks that are allocated to her.
How can I put this in my project plan?

thank you
 
R

Rob Schneider

Setup a Calendar for her, and mark the days that she is available to
work on your project. Double click on the resource name and read about
this in Help (button on that screen).

--rms