hi, how can I use MSP to track resource ultilisation ?
J JulieS Jan 17, 2010 #2 Hello Lynn, Display the Resource Usage view to get a timephased view of Work, or Peak Units, or Overallocation, or Remaining Availability. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project
Hello Lynn, Display the Resource Usage view to get a timephased view of Work, or Peak Units, or Overallocation, or Remaining Availability. I hope this helps. Let us know how you get along. Julie Project MVP Visit http://project.mvps.org/ for the FAQs and additional information about Microsoft Project