R
Rene
Hi,
Something strange is happening when I assign a resource
with 0% Unit (i use it for my generic resource).
If I create a new task, Fixed Unit, Effort Driven, 1 day
dur, 1 hr work. And then I assign a local resource at 0%
Unit, the result is that MSP put the duration to 0 day and
resource unit to 6000%.
This 6000% seams to be equal to 1hr=60mins or 60 Units.
If the Work was initially set to 24 hrs, then the Units
would be 144000%, meaning 24hrs=144000mins.
Does anyone can tell me is this behaviour is normal?
I tried to see if there is any information on the effect
of putting the Assignment Resource Unit to 0%. Any help?
Thanks.
Something strange is happening when I assign a resource
with 0% Unit (i use it for my generic resource).
If I create a new task, Fixed Unit, Effort Driven, 1 day
dur, 1 hr work. And then I assign a local resource at 0%
Unit, the result is that MSP put the duration to 0 day and
resource unit to 6000%.
This 6000% seams to be equal to 1hr=60mins or 60 Units.
If the Work was initially set to 24 hrs, then the Units
would be 144000%, meaning 24hrs=144000mins.
Does anyone can tell me is this behaviour is normal?
I tried to see if there is any information on the effect
of putting the Assignment Resource Unit to 0%. Any help?
Thanks.