Resource Usage across all Projects

C

CSteiz

Accounting wants me to provide a report of hours worked by each resource
against each task they are assigned, on a monthly basis. I've figured
out that Resource Usage reprt shows this for a particular project. But
I cannot seem to get the Resource Usage view accessible to anyone with
rigts across all projects in PWA.

Is there anyway to create a report showing hours worked by each
resource against each task they are assigned, on a monthly basis?

I tried using SQL but cannot track down the table(s) that incorporates
the right timesheet data with dates.

Any help or pointers would be appreciated.
This forum already helped me define the problem better.

Regards,

Chuck
 
Top