Resource Usage - Other Projects and Commitments - Cannot See In wh

E

Erdem Seherler

Hi all;
I have looked at the previous questions but cannot see any answers to my
question so I want to ask it to the group.

I'm using Project Server 2007 and have numerous projects.
In one of my projects I try to level resources and one of my resources get
the first task starting at 01.04.08. I try to find out in which task she
works before that day and I saw that she starts to work in other projects
starting from 13.08.2007 to 10.01.2008 as 0h. But when I look at the details
of the other projects I cannot see any 0h at other projects. How can I find
in which project she is working.

2- Is there any other way for her to make work in my project by leveling,
when she is seen in other project as 0h.

Best Regards,
Erdem
 
E

Erdem Seherler

Some more information:
I have created an empty project,
looking at resource usage and seeing that in other projects and commitments
8.25h is shown,where only 0.25 h is displayed in one of the projects. Where
might be the detail of 8h?
 
Top