Resource Usage Sheet Showing ALL Project Tasks

K

Kevin Flanagan

Recently we had to rebuild our environment. Up until
now, whenever you went in to view resource usage, only
the project you had open was showing. Now it doesn't
make any difference what project you have open, you can
see a resource's assignment in ALL projects in the
database. Any help appreciated.

Thanks,

Kevin
 
G

Gary Chefetz [MVP]

Kevin:

Are you certain that you're not confusing Task Usage with Resource Usage?
The resource usage view always shows all.

--
Gary Chefetz [MVP]
http://www.msprojectexperts.com

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 
M

Matteo Rosi

In that case how should I do to view scheduled work for
each resource but just for my project?
I've tried by filtering for my own project and this shows
actually the allocation of the resources just for my
activities but still the total amount per resource
includes also the other company projects!!

Any suggestion?
 
Top