Resource Usage view as a custom view in PWA

R

Richard Greenall

Is it possible to create a custom view for Resource Usage
in PWA? I see that in-built views for resource
availabilty are similar, however all PWA custom views use
gantt chart.

I believe you can develop and add your own views to the
system which fall outside the capability of the "customise
views" function. Does anyone have the a piece of asp or
other code for this view?

I'm looking for "Resource Usage" and "Task Usage" views as
in the Pro client.

Thanks Richard
 
D

Dale Howard

Richard --

Good question. First of all, the View Resource Assignments view already
allows the user to display a view that looks like Resource Usage and
includes the timephased grid on the right. To do so, click the View
Resource Assignments link in the sidepane, and then click the "Timesheet
format" link at the top of the sidepane.

For the moment, I do not believe it is possible to create a Project view in
PWA containing the timephased grid. Hope this helps.
 