J
Jeff Sweeney
Image a leveled enterprise resource has been scheduled five 8 hour
tasks, via predecessors, to be done one after the other. After the
first day, the resource reports working on the first task for 6 hours
and on the second task for 2 hours. The project is then updated using
the "Update Project" feature and completed portions of tasks are
pulled back to the first day where they were completed while the
uncompleted remainder of those tasks and the other tasks are pushed
out to start after day one. When project is leveled, it shows 8 hours
scheduled for each of the remaining four days in the Resource Usage
View. (This is good.)
However, when I go to another project [and close the first one] on the
server and look at the Resource Usage View, the same enterprise
resource shows over allocated with numbers of hours other than the
8-hour days that my first project showed? (This is bad.)
The resource has no other tasks assigned in any other project for the
period being discussed.
Thanks for any insight you can provide.
tasks, via predecessors, to be done one after the other. After the
first day, the resource reports working on the first task for 6 hours
and on the second task for 2 hours. The project is then updated using
the "Update Project" feature and completed portions of tasks are
pulled back to the first day where they were completed while the
uncompleted remainder of those tasks and the other tasks are pushed
out to start after day one. When project is leveled, it shows 8 hours
scheduled for each of the remaining four days in the Resource Usage
View. (This is good.)
However, when I go to another project [and close the first one] on the
server and look at the Resource Usage View, the same enterprise
resource shows over allocated with numbers of hours other than the
8-hour days that my first project showed? (This is bad.)
The resource has no other tasks assigned in any other project for the
period being discussed.
Thanks for any insight you can provide.