Resource Usage View - Seeing all projects a resource is allocated

S

Simmons_RJ

We are using Project Server 2002 w/ MS Project Pro 2002.

Most project managers within our organization can see all the projects a
resource is allocated to when the look at the resource usage view from with
the project plan they have open. They see the tasks of the plan they have
open and the projects the resources are allocated to.

Other project managers only see the tasks for the plan they have open and do
not see the other projects the resource is allocated to. This does not appear
to be project plan specific.

Can anyone suggest why this is occurring?

Thanks!
 
R

RickD

I your projects are in Server, check to see if your project managers are
using a filter. I believe the default action with no filter is that PM's will
see everywhere a resource is assigned. If the filter is set to Project Team,
you will only see information specific to the one project.
 
Top