We are using Project Server 2002 w/ MS Project Pro 2002.
Most project managers within our organization can see all the projects a
resource is allocated to when the look at the resource usage view from with
the project plan they have open. They see the tasks of the plan they have
open and the projects the resources are allocated to.
Other project managers only see the tasks for the plan they have open and do
not see the other projects the resource is allocated to. This does not appear
to be project plan specific.
Can anyone suggest why this is occurring?
Thanks!
Most project managers within our organization can see all the projects a
resource is allocated to when the look at the resource usage view from with
the project plan they have open. They see the tasks of the plan they have
open and the projects the resources are allocated to.
Other project managers only see the tasks for the plan they have open and do
not see the other projects the resource is allocated to. This does not appear
to be project plan specific.
Can anyone suggest why this is occurring?