Hello Cedric,
My comments/answers are inline below.
CBnation said:
Two questions on Resource usage view
- Can I show the task path? The task summary field shows only the
parent node, but I want the entire path to know which task I'm
looking
at
[Julie] Not directly, no. The resource usage view contains resource
and assignment information. However, you could conceivably add a
text field to the Task Usage view, run a macro to populate the field
with the entire "parentage" of a task, roll it down to assignments
and then, through code (VBA) copy the data from the task assignment
field to the resource assignment field. To that end, Jack Dahlgren
has provided some sample code on his page that will add the full
path string to a text field. See Jack's "SummaryName" macro at:
http://masamiki.com/project/macros.htm
Before running Jack's macro, you'll need to make sure you set the
field (Text12) from the macro to automatically roll down through the
custom field property.
Once you've run Jack's "SummaryName" macro, see the sample code at
FAQ 37 at
http://project.mvps.org/faqs.htm.
- Why is the priority field of the Gantt chart not available in
the
Resource Usage view? When i do Add column, it is not in the list.
[Julie] Because priority is a task field and the Resource Usage view
does not contain tasks, only resources and assignments.
I'm using Project2007
Cedric
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project