Resource Usage

M

Maanu

Hi

Certain tasks in a project (project tracking) will be from the beginning of
the prokject to the end of the project (a single task). If a resource
allocated to this task is assigned to some other tasks there will be
overallocation.

I have corrected this problem by allocating 10% for the project tracking
task and 90% for other tasks.

Is there any other way to solve this problem?

Thanks,
Manu
 
R

Rod Gill

Yes, but your solution is best. If you resource assignments are not
accurate, you don't get a meaningful picture of what your resource needs
are.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Maanu said:
Hi

Certain tasks in a project (project tracking) will be from the beginning
of
the prokject to the end of the project (a single task). If a resource
allocated to this task is assigned to some other tasks there will be
overallocation.

I have corrected this problem by allocating 10% for the project tracking
task and 90% for other tasks.

Is there any other way to solve this problem?

Thanks,
Manu


__________ Information from ESET Smart Security, version of virus
signature database 4959 (20100319) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4959 (20100319) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top