R
Ryan
I'm using Project 2002 Server and 2002 Professional.
I'm a little confused with how a resource is suppose to keep their project
manager updated on work complete using PWA. When in Timesheet view, the
only editable fields are % work complete and remaining work. If a resource
wants to report that they're 50% done with a task, he/she can update the %
work complete field and actual hours worked and remaining duration are
automatically calculated based on the initial time estimate. But what if
the task took half as long as expected? % work complete and actual work
seem to be linked together so you cannot change the values to something like
50% complete in 2 hours (if the task was estimated to take 8 hours).
Also, it seems to me that it would make more sense for resources to update
their hourly timesheet (4 hours working on task1 today, 4 hours on task2,
etc), but these fields are all locked out (greyed). Did I set a permission
incorrectly? The account I am testing with is mine, and I have full
administrative permissions set up.
The most logical choice to me would be to have the resources update their %
work complete as well as hourly timesheet on a daily or weekly basis, but
this does not seem possible. Am I taking the wrong approach to the problem?
Thanks for any advice.
Ryan
I'm a little confused with how a resource is suppose to keep their project
manager updated on work complete using PWA. When in Timesheet view, the
only editable fields are % work complete and remaining work. If a resource
wants to report that they're 50% done with a task, he/she can update the %
work complete field and actual hours worked and remaining duration are
automatically calculated based on the initial time estimate. But what if
the task took half as long as expected? % work complete and actual work
seem to be linked together so you cannot change the values to something like
50% complete in 2 hours (if the task was estimated to take 8 hours).
Also, it seems to me that it would make more sense for resources to update
their hourly timesheet (4 hours working on task1 today, 4 hours on task2,
etc), but these fields are all locked out (greyed). Did I set a permission
incorrectly? The account I am testing with is mine, and I have full
administrative permissions set up.
The most logical choice to me would be to have the resources update their %
work complete as well as hourly timesheet on a daily or weekly basis, but
this does not seem possible. Am I taking the wrong approach to the problem?
Thanks for any advice.
Ryan