What is the best approach to work with tasks that are assigned to a
subcontracting company.
We want to include the task in our project plan and use the company name as
resource name when assigning the task.
Should I use local resources or is there a better way ? I read that it is
not recommended to user local resources that can cause spooler errors...

thanks

Marco
 
V

Vadim Bogdanov

Marco,

just open local resource properties and set Workgroup to None.
This will avoid spooler errors.
 