Dale Howard [MVP]
Chris --
Your Project Server administrator must diable the Managed Time Periods
option to allow the PM to remove the resource and the actual from the
summary task. After the PM completes this action, saves, and publishes the
project, the Project Server administrator can re-enable the Managed Time
Periods option. Hope this helps.
Your Project Server administrator must diable the Managed Time Periods
option to allow the PM to remove the resource and the actual from the
summary task. After the PM completes this action, saves, and publishes the
project, the Project Server administrator can re-enable the Managed Time
Periods option. Hope this helps.