L
Laureen
Hello,
We are trying to see the value in using the Resource Information tab rather
than an administrative project. I am able to enter dates that a resource is
"Available From" and "Available To" and use a % of units. However, when I
then assign that resource to a task within those dates, I am not getting the
proper amount of "Units". It mostly defaults to the Units that was entered
in the 1st set of dates. What am I doing wrong?
Also, I cannot seem to get this "Units" field to appear in neither the MS
Project nor PWA views.
Any thoughts? Thank You!
We are trying to see the value in using the Resource Information tab rather
than an administrative project. I am able to enter dates that a resource is
"Available From" and "Available To" and use a % of units. However, when I
then assign that resource to a task within those dates, I am not getting the
proper amount of "Units". It mostly defaults to the Units that was entered
in the 1st set of dates. What am I doing wrong?
Also, I cannot seem to get this "Units" field to appear in neither the MS
Project nor PWA views.
Any thoughts? Thank You!