L
Louise Anderson
Hello.
I am using Project Server 2003. I saw the post on 3/23 in which a very
similar issue was reported. However, the resolutions reported are not working
for me. I have resources that have tasks assigned to them, however the fields
are not available to them to have actuals added daily on the right-hand side
of the task sheet. The fields that are available are "Actuals" and "Remaining
Work" on the right-hand side of the task sheet. What setting am I missing?
Thank you!
I am using Project Server 2003. I saw the post on 3/23 in which a very
similar issue was reported. However, the resolutions reported are not working
for me. I have resources that have tasks assigned to them, however the fields
are not available to them to have actuals added daily on the right-hand side
of the task sheet. The fields that are available are "Actuals" and "Remaining
Work" on the right-hand side of the task sheet. What setting am I missing?
Thank you!