Resources from Enterprise Resource Pool

A

Andrzej B³och

Hi.
I add new resource to Enterprise Resource Pool. Then I change work time of
the resource to some nondefault values and save the resource.
Is there any way to extract this data from ProjectServer database?
I can find some data in MSP_RESOURCES table (resource name, initials and so
on) , but
what about work time? I can't find it anywhere.

Any hints?
 
G

Garon Line

There is a DBSchema and Entity Relationship diagram in
the Project Server 2003 Resources (Downloads) section.

This may help. I have not had a chance to look through
it completely, so am not sure if it includes the
relationship to the Calendar tables.

You need to be looking for Views tables that are related
to the Resource Calendar (I believe)

Hope this gets you going in the right direction.

Regards
Garon
 