There's an Operations project here that is a one-liner that lasts a given
duration and has about 30+ people reporting time to it.
Each resource is set to 100% units and the fixed duration of 200-some days.
For some reason, there are four resources in the plan with 0h of Remaining
Work. They've already put in 1,000+ Actual Work hours to the plan (start date
was 12/6/04), however in the Resource Schedule view, their finish date
remains 9/30/05 (as it should). I looked at the Resource Usage view and they
all have actual work applied to them right thru 9/30/05!
Any idea how such a thing could occur?
thanks in advance for any help!
duration and has about 30+ people reporting time to it.
Each resource is set to 100% units and the fixed duration of 200-some days.
For some reason, there are four resources in the plan with 0h of Remaining
Work. They've already put in 1,000+ Actual Work hours to the plan (start date
was 12/6/04), however in the Resource Schedule view, their finish date
remains 9/30/05 (as it should). I looked at the Resource Usage view and they
all have actual work applied to them right thru 9/30/05!
Any idea how such a thing could occur?
thanks in advance for any help!