resources have actual work reported thru 9/30/05...

J

jillemo

There's an Operations project here that is a one-liner that lasts a given
duration and has about 30+ people reporting time to it.

Each resource is set to 100% units and the fixed duration of 200-some days.

For some reason, there are four resources in the plan with 0h of Remaining
Work. They've already put in 1,000+ Actual Work hours to the plan (start date
was 12/6/04), however in the Resource Schedule view, their finish date
remains 9/30/05 (as it should). I looked at the Resource Usage view and they
all have actual work applied to them right thru 9/30/05!

Any idea how such a thing could occur?

thanks in advance for any help!
 
D

Dale Howard [MVP]

jillemo --

If the team members in question reported 100% Work Complete on their work on
this task, Microsoft Project Professional will mark all past, current, and
future work as complete, regardless of how far the date is into the future.
Could this have happened?
 