Hi,
I have divided resources in two location based on two departments by using
RBS as following.
1-----Networking
2-----Development
Heads of each department can see only their resources and assign tasks to
them in their projects.
Now the problem is if Development department needs to use the resources of
Network department then how this will be accomplish?
Any help will be highly appreciated
Regards,
MNA