Resources Showin in "Timeline" style?

A

avimia

Hello experts,


Is there any way to show resources (human) in same style as the "Timeline"?

The bar graph in waterfall style works fine in Timeline. But, rather than
that "timeline" showing each task along the way, I would like to show each
bar as each human (resource). So, in esssence I could see what
human-resource's tasks are over-lapping (in a time period) with anothers.
Even better would be to see this per each task. But, I would settle for just
seeing what human is over lapping with another.

Thanks!
 
J

Jan De Messemaeker

Hi,

This is done in Project 2010, it's called the team planner view. Not in
earlier versions I'm afraid.
You could always use the Using Resource... filter in the Gantt Chart view to
see this resource by resource.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
J

JulieS

Hello Avima,

See if the Resource Allocation view gets you close. The resource
allocation view is the Resource Usage view in the top pane and
the leveling Gantt in the lower pane.

By selecting a resource name in the top (Resource usage) pane,
you see the tasks assigned to that specific resource in the lower
pane.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top