Can someone tell me the best way tomanage a resource on
multiple projects in this sense.
I have resources that estimate that it is going to take
them 2 weeks to complete a task, however they get it done
in one week. This affects my other project that had them
scheduled to begin work after the two weeks.
How do I get rid f the gaps between projects?
Thanks
Rick