Resourse Availability not correct in PWA

C

Clark

I hope that someone can help me out with my problem.

When I am looking at a resources availability in PWA, Resources, Selected
Resource then View availability. The available time for any resource shows
the hours that they are available until August 31, 2003. After that it
shows zeros. I have checked the resource calendars and they are setup with
the proper working times and availabilities from and to of NA. I get a
warning message for all of my resources in PWA: View Resource Availability
view stating;

"Warning: Availability data has not been published for one or more resources
in the selected date range."

What I need to do is figure out what is not setup correctly and get it
working.

If anyone could help me out I would appreciate it.

Thanks

Clark
 
G

Gary Chefetz [MVP]

Clark:

Logon to Project Web Access as an administrator
Select Admin > Manage Enterprise Features > OLAP and Resource Availability
(paraphrasing from memory)
Set the availability options as you like and publish availability. This is
set to 4 weeks by default.

--
Gary Chefetz [MVP]
http://www.msprojectexperts.com

*** Remember to look for line breaks in links posted to the news group, use
cut and paste for these.
 
C

Clark

Thanks gary. Worked like a charm.

I see that you released a book on Server. I think that I may just have to
pick it up. Do you deal with RSB codes and server permissions in you book??

That is another issue that I have with Project PRofessional and Server. I
have setuup the RSB codes with Enterprise Global and the Enterprise
Resources, but I cannot get the permissions to work properly.

Thanks again Gary.

Clark
 