Megatran
I have Project 2003 with server.
My problem is with the resources.
I have a resource call Workers and I have 10 of them. Also I have a
lot of tasks (15) that use 2, 3 or 4 of them in my day shift. My
problem is that I have to create a night shift but with only 4 of the
workers. They will continue the task start in the day shift.
If in my project calendar I add the night shift, then the software
will assign my 10 Workers instead of 4 of them. I don't know how to
specify that. Maybe with the RBS structure?
Thanks anybody for help or a hint where to search.
M.
My problem is with the resources.
I have a resource call Workers and I have 10 of them. Also I have a
lot of tasks (15) that use 2, 3 or 4 of them in my day shift. My
problem is that I have to create a night shift but with only 4 of the
workers. They will continue the task start in the day shift.
If in my project calendar I add the night shift, then the software
will assign my 10 Workers instead of 4 of them. I don't know how to
specify that. Maybe with the RBS structure?
Thanks anybody for help or a hint where to search.